Dynamics 365 Project Service Automation: Using Journals to cancel out Task Progress % and Resource Utilization %
Tested on:
Dynamics 365 version 9.0.2, web client
PSA solution version 2.4.3.11
Talk around Resource Utilization % and its behavior is a fairly frequent discussion in the Dynamics Community. MVP Scott LeFante has recently written an excellent article on Project Resource Utilization to bring clarity to what impacts a Bookable Resource’s Utilization %. While this blog post demystifies a small…
Continue Reading Antti Pajunen’s Article on their blog
Dynamics 365 Project Service Automation: Using Journals to cancel out Task Progress % and Resource Utilization %
Blog Syndicated with Antti Pajunen’s Permission
More About This Author
Array
- Dyn365CE10 February 2023Using environment variables in a flow’s Excel action
- Dyn365CE22 January 2023Dynamics 365 Project Operations: Approving time entries using the Project Approver Admin role
- Dyn365CE27 December 2022Time-zone agnostic price defaulting in Project Operations
- Dyn365CE5 December 2022External scheduling in Project Operations