Shawn Tabor wants to know whether to estimate project effort in days or story points. Aren’t they the same thing?

I’ve used four ways of estimating effort in my Dynamics 365 projects:

  1. Counting cards
  2. Days
  3. T-shirts
  4. Story points

Estimating in days is an absolute estimation method, whereas t-shirts and story points are both relative estimation methods. This means that we compare the relative…

Continue Reading Neil Benson’s Article on their blog

28 – Shawn, Stop Estimating Effort in Days

Shawn Tabor wants to know whether to estimate project effort in days or story points. Aren’t they the same thing? I’ve used four ways of estimating effort in my Dynamics 365 projects: Counting cards Days T-shirts Story points Estimating in days is an absolute estimation method, whereas t-shirts and story points are both relative estimation methods.

Blog Syndicated with Neil Benson’s Permission

Leave a reply

Join Us
  • X Network2.1K
  • LinkedIn3.8k
  • Bluesky0.5K
Support The Site
Events
February 2025
MTWTFSS
      1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28   
« Jan   Mar »
Follow
Sign In/Sign Up Sidebar Search
Popular Now
Loading

Signing-in 3 seconds...

Signing-up 3 seconds...