Shawn, Stop Estimating Effort in Days! with Shawn Tabor – YouTube

#28. Shawn Tabor (https://www.linkedin.com/in/shawntabor/) wants to know whether to estimate project effort in days or story points. Aren’t they the same thing?

I’ve used four ways of estimating effort in my Dynamics 365 projects:

  1. Counting cards
  2. Days
  3. T-shirts
  4. Story points

Estimating in days is an absolute estimation method, whereas t-shirts and story points are both relative estimation methods. This means that we compare the relative size of items using a scale, rather than trying to estimate the absolute size.

Story point estimation has several benefits:

• It’s not as critical to know exactly what types of work are included in the estimate
• Story points encourage me to estimate how long it’ll take the team to get the story done, not just me or my part
• Story point estimates don’t need to be re-estimated if our velocity changes if we change our definition of done or our team composition
• Humans are better at relative estimation, which Neil tries to illustrate with the land area of countries.

Shawn, stop estimating Microsoft Business Applications projects in days and start using story points!

Resources
Shawn Tabor on LinkedIn (https://www.linkedin.com/in/shawntabor/)
CRM Hobbit on Twitter (https://twitter.com/CRMhobbit)
CRM Hobbit website (https://crmhobbit.com/)
Support the show (https://buymeacoffee.com/amazingapps)

CONNECT
🌏 Amazing Apps (https://amazingapps.show) website
🟦 Customery on LinkedIn (https://linkedin.com/company/customery)
🟦 Neil Benson on LinkedIn (https://linkedin.com/in/neilbenson)

MY ONLINE COURSES
🚀 Agile Foundations for Microsoft Business Apps (https://customery.com/foundations)
🏉 Scrum for Microsoft Business Apps (https://customery.com/scrum)
📐 Estimating Business Apps (https://customery.com/estimating)

Keep experimenting 🧪
-Neil

source

Author: Neil Benson

Share This Post On
Share via
Copy link
Powered by Social Snap