Scenario 1 – Change of cost and sales price before confirmation of project contract Before project contract confirmation, the time transaction has following actuals transactions: The cost and sales price
Scenario 1 – Change of cost and sales price before confirmation of project contract Before project contract confirmation, the time transaction has following actuals transactions: The cost and sales price
If there are two on-account (milestones) lines on the Straight Line Rev Rec project, with different dimensions, other than the one on the project, for example as below, then rev-rec
Scenario 1 – Rev rec at Invoicing Fee Journal DR Project WIP Sale Value (B/S) – 1000 CR Project Accrued Revenue – Sale value (P&L) – 1000
Today I want to share a small trick I learned this week from a colleague of mine. I wasn’t aware of this possibility and couldn’t find any documentation on this.
Original Post http://axaptamaniac.blogspot.com/2022/02/changing-bill-type-d365-project.html